Content

9.5 Grading of project execution quality

Overview

Item

Description

Purpose

To grade a project on its execution quality

Prerequisite/s

Completion of one year of execution phase

Time for completion

Meeting of Prerequisite + half yearly assessment (September and March)

Resource/s

SF 9.5A:Grading of project execution quality

Process owner

For APS: SRLM

For YPS: CTSA

 

Activities

Sl. No.

Action

Actor

Time for completion

Relevant documents

For YPS

1

Conduct the grading of a

project on its execution quality

CTSA

half yearly +15 days

SF 9.5A:Grading of project execution quality

2

Review by PIA of the assessment

PIA

half yearly +20 days

Review and validate SF 9.5A

3

Validation of the assessment

CTSA

half yearly +25 days

Validate and freeze SF 9.5A

For APS

1

Conduct the grading of a

project on its execution quality

SRLM

half yearly +15 days

SF 9.5A:Grading of project execution quality

2

Review by PIA of the assessment

PIA

half yearly +20 days

Review and validate SF 9.5A

3

Validation of the assessment

SRLM

half yearly +25 days

Validate and freeze SF 9.5A