Content
9.3 Grading of batch training quality
Overview
Item |
Description |
Purpose |
To grade quality of training given to a batch |
Prerequisite/s |
Completion of a batch |
Time for completion |
Completion of Training of a batch + 15 working days |
Resource/s |
|
Process owner |
For APS: SRLM For YPS: CTSA |
Activities
Sl. No. |
Action |
Actor |
Time for completion |
Relevant documents |
For YPS |
||||
1 |
Conduct the assessment of the training quality |
CTSA |
Completion of batch+15 working days |
|
2 |
Review by PIA of the assessment |
PIA |
Verification of training quality of a batch by CTSA+30 days |
Review and validate SF 9.3A |
3 |
Validation of the assessment |
CTSA |
Verification of Placement of a batch by CTSA+35 days |
Validate and freeze SF 9.3A |
For APS |
||||
1 |
Conduct the assessment of the training quality |
SRLM |
Completion of batch+15 working days |
|
2 |
Review by PIA of the assessment |
PIA |
Verification of Placement of a batch by SRLM+30 days |
Review and validate SF 9.3A |
3 |
Validation of the assessment |
SRLM |
Verification of Placement of a batch by SRLM+35 days |
Validate and freeze SF 9.3A |