Content
9.2 Grading of physical infrastructure of a training centre
9.2.1 Grading of physical infrastructure of a training centre without residential facilities
Overview
Item |
Description |
Purpose |
To grade a training centre without residential facilities on basis of its physical infrastructure |
Prerequisite/s |
Successful completion of due diligence procedure |
Time for completion |
Due-diligence +17 working days |
Resource/s |
SF 9.2A: Assessment of physical infrastructure after due diligence |
Process owner |
For APS: SRLM For YPS: CTSA |
Activities
Sl. No. |
Action |
Actor |
Time for completion |
Relevant documents |
For YPS |
||||
1 |
Assessment after due diligence |
CTSA |
Due diligence + 10 days |
SF 9.2A: Assessment of physical infrastructure after due diligence |
2 |
Review by PIA of the assessment |
PIA |
Due diligence + 15 days |
Review and validate SF 9.2A |
3 |
Validation of the assessment |
CTSA |
Due diligence + 17 days |
Validate and freeze SF 9.2A |
For APS |
||||
1 |
Assessment after due diligence |
SRLM |
Due diligence + 10 days |
SF 9.2A: Assessment of physical infrastructure after due diligence |
2 |
Review by PIA of the assessment |
PIA |
Due diligence + 15 days |
Review and validate SF 9.2A |
3 |
Validation of the assessment |
SRLM |
Due diligence + 17 days |
Validate and freeze SF 9.2A |
9.2.2 Grading of physical infrastructure of training centre with residential facilities
Overview
Item |
Description |
Purpose |
To grade a training centre on basis of its physical infrastructure with residential facilities |
Prerequisite/s |
Successful completion of due diligence procedure |
Time for completion |
Due diligence +17 working days |
Resource/s |
SF 9.2B: Assessment of physical infrastructure after due diligence |
Process owner |
For APS: SRLM For YPS: CTSA |
Activities
Sl. No. |
Action |
Actor |
Time for completion |
Relevant documents |
For YPS |
||||
1 |
Assessment after due diligence |
CTSA |
Due diligence + 10 days |
SF 9.2B: Assessment of physical infrastructure after due diligence |
2 |
Review by PIA of the assessment |
PIA |
Due diligence + 15 days |
Review and validate SF 9.2B |
3 |
Validation of the assessment |
CTSA |
Due diligence + 17 days |
Validate and freeze SF 9.2B |
For APS |
||||
1 |
Assessment after due diligence |
SRLM |
Due diligence + 10 days |
SF 9.2B: Assessment of physical infrastructure after due diligence |
2 |
Review by PIA of the assessment |
PIA |
Due diligence + 15 days |
Review and validate SF 9.2B |
3 |
Validation of the assessment |
SRLM |
Due diligence + 17 days |
Validate and freeze SF 9.2B |
9.2.3 Resolving differences during assessment
In case of difference of opinion in the assessment team during due diligence, NIRD&PR will take the final decision and grading will be done accordingly. To enable this the due diligence team should reproduce sufficient evidence to the national assessment team. The evidence could be written documents, photographs and videos but it should be authenticated by the team.
However a PIA can file an appeal to MoRD. MoRD should give its decision within 20 working days and that will be treated as binding. However, if MoRD does not give decision in 20 days, then the decision taken by NIRD&PR will be considered final.