Content
3.6. Completion of project training and placement - Issue project completion report
Overview
Item |
Description |
Purpose |
To verify and close the training and placement component of the project |
Reference to Guidelines |
NA
|
Prerequisite/s |
Completion of project training and placement activities |
Time for completion |
Complete within 70 days after the PIA completes the project training and placement process. (Date of completion of placement for the project is referred as ‘E7’ day). |
Resource/s |
|
Process owner |
For APS: SRLM/For YPS: CTSA |
Activities
Actor |
Action |
Time for completion |
Relevant Documents |
PIA op team |
1. Complete last batch of training and place minimum 75% of candidates thereof. System will freeze the training and placement data on the designated website 2. Provide the checklist as per standard format |
E6 for training and E7 for placement completion |
Nil |
PIA Q team |
Complete the verification of training and placement |
E7 + 20 days |
Nil |
SRLM (For APS)/ CTSA (For YPS ) |
Complete the verification of training and placement |
E7 + 20 days |
Nil |
SRLM (For APS)/ CTSA (For YPS) |
Validate the training and placement data on the designated website |
E7+ 35day |
Nil |
SRLM/CTSA |
Ensure all advisories are complied with – advisories from CTSA to SRLM for APS and vice-versa for YPS. |
E7+ 40 days |
Inspection report of Q teams of SRLM/ CTSA |
For APS |
|||
SRLM |
Verify the check list and finalise the total training and placement |
E7 + 45 days |
|
SRLM |
Issue Project completion report |
E7 + 70 days |
Nil |
For YPS |
|||
CTSA |
Verify the check list and finalise the total training and placement |
E7 +45 days |
|
CTSA |
Advise MoRD about the project closure of training and placement |
E7 +50 days |
Nil |
MoRD |
Issue project completion report |
E7 +70 days |
Nil |