Print bookPrint book

Content

Site: eSOP Learning Portal
Course: Operations
Book: Content
Printed by: Guest user
Date: Thursday, 24 July 2025, 4:49 AM

Table of contents

3.1. MoU Execution

Overview

Item

Description

Purpose

To lay down MoU execution process and related timelines

Reference to Guidelines

Step 6 & 7, table 4, Para 4.1, pages 36 and 45

Prerequisite/s

Uploading of approved empowered committee (EC) minutes and sanction order

Time for completion                  

20 working days from uploading of sanction order on the nominated website (Sanction order uploading day is referred as ‘I2’)

Resource/s

As per SF 3.1A: Prospective project work schedule, SF 3.1B: Standard terms & condition, SF 3.1.C: Special terms & conditions and SF 3.1.D: Power of Attorney (PoA)

Process owner

For APS: SRLM

For YPS: CTSA

3.1.1     Preparatory work for execution of MoU

Overview

Item

Description

Purpose

To delineate the preparatory work for MoU execution and related timelines

Prerequisite/s

Uploading of EC minutes on the nominated website

Time for completion

15 days of time gap between I1 and I2 and 2 days after I2(I1: Uploading of approved EC minutes and I2: Uploading of Sanction order)

Resource/s

As per SF 3.1A: Prospective project work scheduleSF 3.1B: Standard terms & condition, SF 3.1.C: Special terms & conditions and SF 3.1.D: Power of Attorney (PoA)

Process owner

For APS: SRLM

For YPS: CTSA

 

Activities

Sl.

Action

Actor

Time for completion

Relevant documents

For YPS

1

Filling up “Prospective project work schedule”

PIA

I1 + 10days

SF 3.1A: Prospective project work schedule

2

Review of “Prospective project work schedule”[1]

SRLM

I1 + 15 days

Review and validate SF 3.1Aas per 3.1.1.1 of SOP

3

Validation of “Prospective project work schedule”

CTSA

I1+ 17days

validate and freeze SF 3.1A as per 3.1.1.1 of SOP

4

Preparation of MoU annexures

PIA

I1+3 days

SF 3.1B: Standard terms & condition, SF 3.1.C: Special terms & conditions and SF 3.1.D: Power of Attorney (PoA)

5

Filling up MoU signatory by name & designation

PIA, SRLM &CTSA

I1 +3 days

On the designated website

6

Review fund position and advise MoRD and/or SRLM if funds are likely to fall short with a copy to PIA

CTSA

I1 +3 days

As per data given in ERP system.

For APS

1

Filling up “Prospective project work schedule”

PIA

I1 +10 days

SF 3.1A

2

Validation of “Prospective project work schedule”

SRLM

I1 +17 days

validate and freeze SF 3.1A as per 3.1.1.1 of SOP below

3

Preparation of MoU annexures

PIA

I1 +3 days

SF 3.1B, 3.1.1C and 3.1.1D

4

Filling of MoU signatory by name & designation

PIA and SRLM

I1 +3 days

On the designated website

5

Review fund position and advise MoRD or take internal action if funds are likely to fall short with a copy to PIA.

SRLM

I1 +3 days

As per data given in ERP system.

 

3.1.1.1     Prospective work schedule for the project: Contents and relevance

The prospective work schedule for the project should give a comprehensive picture of PIA’s plan of action for implementing the project. The details are to be filled in a web form as per SF 3.1A and would include the following:

a. Monthly training commencement schedule for the complete project duration.

b. Monthly training completion schedule for the complete project duration.

c. Training of candidates should commence within 90 days of project commencement date.

Figure 3.1Preparatory steps in execution of MoU for YPS

d. Minimum trainings to be initiated in a year as per the project duration is given below:

e. Within the minimum targets prescribed above the PIA has flexibility to vary the training quantum across different months of the year, across different geographical locations, across different trades and training     centres.

f.  Within the minimum yearly targets prescribed above the PIAs has flexibility to revise the PPWS as per the conditions prescribed below:

3.1.1.2     Monitoring of the prospective work schedule

Any deviation from PPWS will lead to:

3.1.2     Signing of MoU

Overview

Item

Description

Purpose

To delineate the steps/actions to be taken in signing MoU

Prerequisite/s

Uploading of sanction order on the nominated website

Time for completion

20 working days from uploading of sanction order (start from I2day)

Resource/s

MoU

Process owner

For APS: SRLM

For YPS: CTSA

Activities

Sl.

Action

Actor

Time for completion

Relevant Documents

For YPS

1

Review highlighted text of system generated MoU

PIA & SRLM

I2+2 days

MoU

2

Vetting and freezing of MoU and annexures thereof

CTSA

I2+4 days

MoU

3

Printing and signing of MoU and annexures, and ensure that it reaches SRLM

PIA

I2+7 days

From the above source

4

Signing of MoU and ensuring that it reaches CTSA

SRLM

I2+14 days

MoU

5

  1. Signing of MoU and ensuring that copies reach SRLM and PIA
  2. Uploading of MoU and annexures on the web-link

CTSA

I2+20 days

MoU and uploading on the designated website

For APS

1

Review highlighted text of system generated MoU

PIA

I2+2 days

MoU

2

Vetting and freezing of MoU and annexures thereof

SRLM

I2+4 days

MoU

3

Printing and signing of MoU and annexures, which should reach at SRLM

PIA

I2+7 days

From the above source

4

Signing of MoU sending a copy to PIA and informing CTSA about the event completion

Uploading MoU and annexures on the web-link

SRLM

I2+14 days

Project MoU and uploading on the designated website

 

Figure 3.1‑2 Execution of MoU for YPS

 

3.2. Release of 1st instalment

Overview

Item

Description

Purpose

To lay down the fund release process for 1st instalment and issue of Project commencement order to PIA

Reference to Guidelines

 Row 1, Instalment 1, table 6, para 5.9, page 56

Prerequisite/s                    

Uploading of executed MoU

Time for completion                   

10 working days after signing the MoU (MoU execution day is coded as I3)

Resource/s               

As per SF 3.2A: Project account registration form on PFMS and SF 3.2B: Project commencement order and SI 8.3D1: Applicability and settlement of TDS

Process owner:

For APS: SRLM

For YPS: CTSA

Activities

Actor

Action

Time for completion

Relevant Documents

PIA

  1. Opening dedicated bank account[1] for the project and linking it to Public Finance Monitoring System (PFMS)
  2. Filling up the bank account details if PFMS is not operational.

To be completed at least 5 days before signing of MoU (I3-5 days)

SF 3.2A: Project account registration form on PFMS

SRLM

(For APS)/ CTSA

(For YPS)

Release the first instalment amount of central & State shares after deduction of TDS and updating the status on designated web-link (It is mandatory central and state shares are released together This should be followed meticulously by fund releasing agencies)

latest by I3+10 days

SI 8.3D1: Applicability and settlement of TDS

SRLM

(For APS)/ CTSA

(For YPS)

Issue of Project commencement order

latest byI3+10 days

SF 3.2B: Project commencement order

Note: The project commencement date of the project will be from 30 days from the date release of central and state share from CTSA for YPS/ SRLM for APS

 

CTSA must release funds to the PIAs only after it receives both the central and state shares. In some cases the central share was released before the SOP was issued with the instructions that PIA should not spend any money till SOP is released. Now it is reiterated that PIA should not spend any money till state share is released.


[1] If consortium partners are going to implement any activities and any outsourcing partner is engaged in training and placement towards the project, they have to open a dedicated bank account. All the project bank account needs to be mapped into PFMS, whenever the system becomes functional.

3.3.Project Execution Readiness Assessment

Overview

Item

Description

Purpose

To ensure availability of basic core team for implementing the project and sensitize them in implementation procedures

Reference to Guidelines

 NA

Prerequisite/s                    

Uploading of sanction order on the designated website

Time for completion                  

Any time after issue of sanction order but not later than 30 days from release of 1st Instalment (not later than I +30) and continuous process for revision

Resource/s                

SF 3.3A: Project execution readiness assessment at Project Headquarter and SF 3.3A1: Project execution readiness assessment at PIA Headquarter

Process owner

PIA for all states

Activities

Actor

Action

Time for completion

Relevant Documents

PIA

  • Filling up all the details

  • Update planned change

  • Update unplanned change

Not later than I + 15 days

15 days before change

Within 48 hours of change

SF 3.3A: Project execution readiness assessment at Project Headquarter and SF 3.3A1: Project execution readiness assessment at PIA Headquarter

SRLM (for APS)/CTSA (for YPS)

  • Validation of data and visit of project Headquarter

First visit: Complete by I + 30 days

Other visits: Not specified but will be decided based on the quality of project implementation.

SF 3.3A: Project execution readiness assessment at Project headquarter

SRLM (for APS)/CTSA (for YPS)

  • Validation of data and visit of PIA Headquarter*.

To be done along with first month audit visit by Finance team.

Other visits: Not specified but will be decided based on the quality of project implementation subject to minimum of one visit in a year either by  CTSA or SRLM visit. Others can decide based on the visit report.

SF 3.3A: Project execution readiness assessment at Project Headquarter

Note: As a PIA may have projects spread out in many states the teams can plan the visits in consultation PIA and other states. If a SRLM/CTSA team visit is less than 6 months old, then PIA headquarter visit is optional. SRLM/CTSA can take a call depending on the situation.

3.4. Release of 2nd instalment

Overview

Item

Description

Purpose

To specify activities for release of 2nd instalment of funds to PIA

Reference to Guidelines

Row 2, instalment 2, table 6, para 5.9, page 56

Prerequisite/s                    

System generated notification for fulfilment of condition as per above reference to guidelines

Time for completion                   

60 working days for YPS (40 working days for APS) from eligibility day (notification date of eligibility for 2nd instalment is coded as E2) provided all conditions are fulfilled by the PIA.

Resource/s                

SF 3.4A: Checklist for release of 2nd instalment updated through the system and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment.

Process owner

for APS: SRLM

for YPS

1) CTSA till dispatch of recommendation to MoRD and also for release of funds after MoRD issues release order

2) MoRD after receipt of recommendation and till issue of release order

Activities

Actor

Action

Time for completion

Relevant Documents

PIA

Submission of checklist and annexures for release of 2nd instalment to SRLM for APS/CTSA for YPS

E2+3 days

SF 3.4A: Checklist for release of 2nd instalment updated through the system and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment

SRLM for APS/CTSA for YPS

Ensure all advisories are complied with CTSA to SRLM for APS and vice-versa for YPS. Validate the checklist, annexures and upload on designated web-link.[1]

 E2 +10 days

Inspection reports of PIA Q team, SRLM/CTSA and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment

For APS

SRLM

(APS)

  1. Issue of release order & upload on the designated web-link
  2. Release 2nd  instalment amount of Central  and State share to PIA’s designated bank account for the project after deducting TDS.
  3. Update fund release status on the designated web-link

Before E2+40 days

SI 8.3D1: Applicability and settlement of TDS

For YPS

CTSA

 

Recommendation for release of 2nd instalment to MoRD

E2 +12 days

SF 3.4A: Checklist for release of 2nd instalment updated through the system

MoRD

Issue of release order and upload on the designated web-link

E2+ 52 days

Nil

CTSA

Release of 2nd instalment to PIA after deducting TDS and upload the status on the designated web-link

E2+60 days

SI 8.3D1: Applicability and settlement of TDS



[1]If a PIA fails to comply with the conditions for release of instalment then the request for release will be sent to the bottom of queue.

3.5. Release of 3rd instalment

Overview

Item

Description

Purpose

To delineate steps in release of 3rd instalment to PIA

Reference to Guidelines

Row 3, instalment 3, table 6, para 5.9, page 56

Prerequisite/s                    

System generated notification for fulfilment of condition as per above reference to guidelines

Time for completion                   

60 working days for YPS (40 working days for APS) from eligibility day (notification date of eligibility for 3nd instalment is referred as ‘E4’ day) provided all conditions are fulfilled by the PIA.

Resource/s                

SF 3.5A: Checklist for release of 3rd instalment and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment

Process owner

for APS: SRLM

for YPS

1) CTSA till dispatch of recommendation to MoRD and also for release of funds after MoRD issues release order.

2) MoRD after receipt of recommendation and till issue of release order

Activities

Actor

Action

Time for completion

Relevant Documents

PIA

Submission of checklist and annexures for release of 3rdinstalment to SRLM for APS/CTSA for YPS

E4+3 days

SF 3.5A: Checklist for release of 3rd instalment and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment

SRLM for APS/CTSA for YPS

Ensure all advisories are compiled by CTSA to SRLM for APS and vice-versa for YPS. Validate the checklist, annexures and upload on designated web-link.[1]

E4+10 days

Inspection report of SRLM/CTSA

For APS

SRLM

(APS)

  1. Issue of release order & upload on the designated web-link
  2. Release 3rdinstalment amount of Central  and State share to PIA’s designated bank account for the project after deducting TDS
  3. Update fund release status on the designated web-link

E4+40 days

SI 8.3D1: Applicability and settlement of TDS

For YPS

CTSA

 

Recommendation for release of 3rdinstalment to MoRD

E4+12 days

SF 3.5A: Checklist for release of 3rd instalment

MoRD

Issue of release order and upload on the designated web-link

E4+52 days

Nil

CTSA

Release of 3rdinstalment to PIA after deducting TDS and upload the status on the designated web-link

E4+60 days

SI 8.3D1: Applicability and settlement of TDS



[1]If it is found that, the PIA has fail to comply the Guidelines condition then the proposal for release will be sent back to the queue and the process will start afresh from the beginning

3.6. Completion of project training and placement - Issue project completion report

Overview

Item

Description

Purpose

To verify and close the training and placement component of the project

Reference to Guidelines

NA

 

Prerequisite/s

Completion of project training and placement activities

Time for completion

Complete within 70 days after the PIA completes the project training and placement process. (Date of completion of placement for the project is referred as ‘E7’ day).

Resource/s

SF 3.7B Project completion report

Process owner

For APS: SRLM/For YPS: CTSA

Activities

Actor

Action

Time for completion

Relevant Documents

PIA op team

1. Complete last batch of training and place minimum 75% of candidates thereof. System will freeze the training and placement data on the designated website

2. Provide the checklist as per standard format

E6 for training and E7 for placement completion

Nil

PIA Q team

Complete the verification of training and placement

E7 + 20 days

Nil

SRLM

(For APS)/ CTSA (For YPS  )

Complete the verification of training and placement

E7 + 20 days

Nil

SRLM

(For APS)/ CTSA (For YPS)

Validate the training and placement data on the designated website

E7+ 35day

Nil

SRLM/CTSA

Ensure all advisories are complied with – advisories from CTSA to SRLM for APS and vice-versa for YPS.

E7+ 40 days

Inspection report of Q teams of SRLM/ CTSA

For APS

SRLM

Verify the check list and finalise the total training and placement

E7 + 45 days

SF 3.7B Project completion report

SRLM

Issue Project completion report

E7 + 70 days

Nil

For YPS

CTSA

Verify the check list and finalise the total training and placement

E7 +45 days

SF 3.7B Project completion report

CTSA

Advise MoRD about the project closure of training and placement

E7 +50 days

Nil

MoRD

Issue project completion report

E7 +70 days

Nil

3.7. Release of 4th instalment and closure of project

Overview

Item

Description

Purpose

To lay down the fund release process of 4th instalment to PIA & closure of the project

Reference to Guidelines

Row 4, instalment 4, table 6, para 5.9, page 56

Prerequisite/s                  

Fulfilment of condition as per reference to guidelines and notification for data freezing on the web-link

Time for completion 

14 months from ‘E7’ day[1]

Resource/s                

SF 3.7A: Checklist for release of 4th instalment and SF 3.7B Project completion report and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment

Process owner

SRLM for APS/CTSA for YPS

Activities

Actor

Action

Time for completion

Relevant Documents

PIA op team

Submission of project closure report and checklist and annexures for release of 4th instalment to SRLM and CTSA

E7+10 months

SF 3.7A: Checklist for release of 4th instalment, SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment and SF 3.7B Project completion report

SRLM for APS/CTSA for YPS

Completing the retention verification process

E7+10 months 9 days

Inspection report of SRLM/CTSA

SRLM for APS/CTSA for YPS

Verification and comments on Project closure report. Validate the checklist, annexures and upload on designated web-link.

E7+10 months 14 days

SF 3.7A: Checklist for release of 4th instalment, SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment and SF 3.7B Project completion report

PIA

Changes as per the comments of SRLM/CTSA (if any)

E7+10 months 24 days

3.7B Project completion report

SRLM for APS/CTSA for YPS

Freezing and uploading of Project closure report on the designated web-link

E7+ 11 months 8 days

3.7B Project completion report

For APS

SRLM

  1. Issue of release order & upload on the designated web-link
  2. Release 4th instalment amount of Central  and State share to PIA’s designated bank account for the project after adjusting/deducting TDS
  3. Update fund release status on the designated web-link
  4. Issue of final closure report

E7+12 months

 

 

E7+12 months 7 days

 

 

 E7+12 months 15 days

E7+13 months

 

SI 8.3D1: Applicability and settlement of TDS

For YPS

CTSA

 

Recommendation for release of 4th instalment to MoRD

E7+11 months 20 days

SF 3.7A Checklist for release of 4th instalment

MoRD

Issue of release order and upload on the designated web-link

E7+13 months 

Nil

CTSA

Release of 4th instalment to PIA after adjusting/deducting TDS and upload the status on the designated web-link

E7+13 months

15 days

SI 8.3D1: Applicability and settlement of TDS

MoRD

Issue of final closure report

E7+14 months

 



[1] References to months and days in this process are to calendar months and days. 

3.8. Consortium arrangements & outsourcing of activities

The basic conditions to be fulfilled for participation of a consortium in DDU-GKY and/or franchising/outsourcing of some activities to other agencies will be as per conditions specified in the guidelines (refer section v and vi, para 4.7 pages 49, 50 and 47 respectively). These conditions will be enforced at the application stage. Following arrangements enable implementation of these conditions:

  1. Consortium

 2.  Outsourcing / Franchisee arrangement

The financial transactions will be transparent and done through PFMS. Till such time PFMS is in place all transactions between various agencies in the project should be done through the banking system only.

If these conditions are not met, a PIA is deemed to have defaulted and action can be initiated as per the rules.

3.9. Orderly closure of a project

A project can be closed/terminated under the following conditions:

3.10. Project manpower plan: Ring fencing Q team from operations

Project manpower is broadly divided into the following three categories:

  1. The management (including Q team head)
  2. Operations team and
  3. Q team

A PIA will have absolute discretion for recruitment of the project management team (other than Q team head) and operations team. However, each month he should inform the total number of people working in each category on a project. CTSA/SRLM will have the discretion to verify these details as per situational exigencies. These will be as per SF 3.10A: Details of centre in-charge and trainers.

Q team head and its composition should be as per agreed plan and the PIA should update the details on the web-link. Similarly changes in the composition of the team should be informed without fail. These should be reported as per SF 3.10B: Details of Q team members.

The Q team should be ring fenced from the PIA operational team and managerial team. Mechanism for ring fencing a PIA Q team is given as SF 3.10C: Ring fencing of Q team from operations – Compliances report from the management. PIA should comply with this procedure before the project is initiated.. 

3.11. Recovery of dues from a PIA

If a PIA defaults in implementing a project, recovering government money paid to PIA after adjusting for expenses incurred as per guidelines and SOP is a critical activity. If the PIA fails to repay the amount it is necessary to invoke the revenue recovery act 1890 or other applicable Revenue Recovery or Public Demands Recovery Act of the state/UT.

The procedure to recover the Government dues is as follows:

 

3.12. List of standard forms in chapter 3

SF 3.1A: Prospective project work schedule

SF 3.1B: Standard terms & conditions

SF 3.1C: Special terms & conditions

SF 3.1D: Power of Attorney

SF 3.2A: Bank account details

SF 3.2B: Project commencement order

SF 3.3A: Project execution readiness assessment

SF 3.4A: Checklist for release of 2nd instalment

SF 3.5A: Checklist for release of 3rd instalment

SF 3.7A: Checklist for release of 4th instalment

SF 3.7B: Project closure report on the completion of project

SF 3.10A: Details of Centre in-charge and trainers

SF 3.10B: Details of Q team members

SF 3.10C: Ring fencing of Q Team from operations – Compliance report from the management