3.4. Release of 2nd instalment
Overview
Item |
Description |
Purpose |
To specify activities for release of 2nd instalment of funds to PIA |
Reference to Guidelines |
|
Prerequisite/s |
System generated notification for fulfilment of condition as per above reference to guidelines |
Time for completion |
60 working days for YPS (40 working days for APS) from eligibility day (notification date of eligibility for 2nd instalment is coded as E2) provided all conditions are fulfilled by the PIA. |
Resource/s |
SF 3.4A: Checklist for release of 2nd instalment updated through the system and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment. |
Process owner |
for APS: SRLM for YPS 1) CTSA till dispatch of recommendation to MoRD and also for release of funds after MoRD issues release order 2) MoRD after receipt of recommendation and till issue of release order |
Activities
Actor |
Action |
Time for completion |
Relevant Documents |
PIA |
Submission of checklist and annexures for release of 2nd instalment to SRLM for APS/CTSA for YPS |
E2+3 days |
SF 3.4A: Checklist for release of 2nd instalment updated through the system and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment |
SRLM for APS/CTSA for YPS |
Ensure all advisories are complied with CTSA to SRLM for APS and vice-versa for YPS. Validate the checklist, annexures and upload on designated web-link.[1] |
E2 +10 days |
Inspection reports of PIA Q team, SRLM/CTSA and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment |
For APS |
|||
SRLM (APS) |
|
Before E2+40 days |
SI 8.3D1: Applicability and settlement of TDS |
For YPS |
|||
CTSA
|
Recommendation for release of 2nd instalment to MoRD |
E2 +12 days |
SF 3.4A: Checklist for release of 2nd instalment updated through the system |
MoRD |
Issue of release order and upload on the designated web-link |
E2+ 52 days |
Nil |
CTSA |
Release of 2nd instalment to PIA after deducting TDS and upload the status on the designated web-link |
E2+60 days |
SI 8.3D1: Applicability and settlement of TDS |
[1]If a PIA fails to comply with the conditions for release of instalment then the request for release will be sent to the bottom of queue.