3.3.Project Execution Readiness Assessment
Overview
Item |
Description |
Purpose |
To ensure availability of basic core team for implementing the project and sensitize them in implementation procedures |
Reference to Guidelines |
NA |
Prerequisite/s |
Uploading of sanction order on the designated website |
Time for completion |
Any time after issue of sanction order but not later than 30 days from release of 1st Instalment (not later than I4 +30) and continuous process for revision |
Resource/s |
SF 3.3A: Project execution readiness assessment at Project Headquarter and SF 3.3A1: Project execution readiness assessment at PIA Headquarter |
Process owner |
PIA for all states |
Activities
Actor |
Action |
Time for completion |
Relevant Documents |
PIA |
|
Not later than I4 + 15 days Within 48 hours of change |
SF 3.3A: Project execution readiness assessment at Project Headquarter and SF 3.3A1: Project execution readiness assessment at PIA Headquarter |
SRLM (for APS)/CTSA (for YPS) |
|
First visit: Complete by I4 + 30 days Other visits: Not specified but will be decided based on the quality of project implementation. |
SF 3.3A: Project execution readiness assessment at Project headquarter |
SRLM (for APS)/CTSA (for YPS) |
|
To be done along with first month audit visit by Finance team. Other visits: Not specified but will be decided based on the quality of project implementation subject to minimum of one visit in a year either by CTSA or SRLM visit. Others can decide based on the visit report. |
SF 3.3A: Project execution readiness assessment at Project Headquarter |
Note: As a PIA may have projects spread out in many states the teams can plan the visits in consultation PIA and other states. If a SRLM/CTSA team visit is less than 6 months old, then PIA headquarter visit is optional. SRLM/CTSA can take a call depending on the situation. |