3.7. Release of 4th instalment and closure of project
Overview
| 
 Item  | 
 Description  | 
| 
 Purpose  | 
 To lay down the fund release process of 4th instalment to PIA & closure of the project  | 
| 
 Reference to Guidelines  | 
|
| 
 Prerequisite/s  | 
 Fulfilment of condition as per reference to guidelines and notification for data freezing on the web-link  | 
| 
 Time for completion    | 
 14 months from ‘E7’ day[1]  | 
| 
 Resource/s  | 
 SF 3.7A: Checklist for release of 4th instalment and SF 3.7B Project completion report and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment  | 
| 
 Process owner  | 
 SRLM for APS/CTSA for YPS  | 
Activities
| 
 Actor  | 
 Action  | 
 Time for completion  | 
 Relevant Documents  | 
| 
 PIA op team  | 
 Submission of project closure report and checklist and annexures for release of 4th instalment to SRLM and CTSA  | 
 E7+10 months  | 
 SF 3.7A: Checklist for release of 4th instalment, SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment and SF 3.7B Project completion report  | 
| 
 SRLM for APS/CTSA for YPS  | 
 Completing the retention verification process  | 
 E7+10 months 9 days  | 
 Inspection report of SRLM/CTSA  | 
| 
 SRLM for APS/CTSA for YPS  | 
 Verification and comments on Project closure report. Validate the checklist, annexures and upload on designated web-link.  | 
 E7+10 months 14 days  | 
 SF 3.7A: Checklist for release of 4th instalment, SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment and SF 3.7B Project completion report  | 
| 
 PIA  | 
 Changes as per the comments of SRLM/CTSA (if any)  | 
 E7+10 months 24 days  | 
|
| 
 SRLM for APS/CTSA for YPS  | 
 Freezing and uploading of Project closure report on the designated web-link  | 
 E7+ 11 months 8 days  | 
 3.7B Project completion report  | 
| 
 For APS  | 
|||
| 
 SRLM  | 
  | 
 E7+12 months 
 
 E7+12 months 7 days 
 
  E7+12 months 15 days E7+13 months 
  | 
 SI 8.3D1: Applicability and settlement of TDS  | 
| 
 For YPS  | 
|||
| 
 CTSA 
  | 
 Recommendation for release of 4th instalment to MoRD  | 
 E7+11 months 20 days  | 
|
| 
 MoRD  | 
 Issue of release order and upload on the designated web-link  | 
 E7+13 months  | 
 Nil  | 
| 
 CTSA  | 
 Release of 4th instalment to PIA after adjusting/deducting TDS and upload the status on the designated web-link  | 
 E7+13 months 15 days  | 
 SI 8.3D1: Applicability and settlement of TDS  | 
| 
 MoRD  | 
 Issue of final closure report  | 
 E7+14 months  | 
 
  |