Content

9.2 Grading of physical infrastructure of a training centre

9.2.1 Grading of physical infrastructure of a training centre without residential facilities

Overview

Item

Description

Purpose

To grade a training centre without residential facilities on basis of its physical infrastructure

Prerequisite/s

Successful completion of due diligence procedure

Time for completion

Due-diligence +17 working days

Resource/s

SF 9.2A: Assessment of physical infrastructure after due diligence

Process owner

For APS: SRLM

For YPS: CTSA

 Activities

Sl. No.

Action

Actor

Time for completion

Relevant documents

For YPS

1

Assessment after due diligence

CTSA

Due diligence + 10 days

SF 9.2A: Assessment of physical infrastructure after due diligence

2

Review by PIA of the assessment

PIA

Due diligence + 15 days

Review and validate SF 9.2A

3

Validation of the assessment

CTSA

Due diligence + 17 days

Validate and freeze SF 9.2A

For APS

1

Assessment after due diligence

SRLM

Due diligence + 10 days

SF 9.2A: Assessment of physical infrastructure after due diligence

2

Review by PIA of the assessment

PIA

Due diligence + 15 days

Review and validate SF 9.2A

3

Validation of the assessment

SRLM

Due diligence + 17 days

Validate and freeze SF 9.2A

 

9.2.2  Grading of physical infrastructure of training centre with residential facilities

Overview

Item

Description

Purpose

To grade a training centre on basis of its physical infrastructure with residential facilities

Prerequisite/s

Successful completion of due diligence procedure

Time for completion

Due diligence +17 working days

Resource/s

SF 9.2B: Assessment of physical infrastructure after due diligence

Process owner

For APS: SRLM

For YPS: CTSA

 Activities

Sl. No.

Action

Actor

Time for completion

Relevant documents

For YPS

1

Assessment after due diligence

CTSA

Due diligence + 10 days

SF 9.2B: Assessment of physical infrastructure after due diligence

2

Review by PIA of the assessment

PIA

Due diligence + 15 days

Review and validate SF 9.2B

3

Validation of the assessment

CTSA

Due diligence + 17 days

Validate and freeze SF 9.2B

For APS

1

Assessment after due diligence

SRLM

Due diligence + 10 days

SF 9.2B: Assessment of physical infrastructure after due diligence

2

Review by PIA of the assessment

PIA

Due diligence + 15 days

Review and validate SF 9.2B

3

Validation of the assessment

SRLM

Due diligence + 17 days

Validate and freeze SF 9.2B

9.2.3  Resolving differences during assessment

In case of difference of opinion in the assessment team during due diligence, NIRD&PR will take the final decision and grading will be done accordingly. To enable this the due diligence team should reproduce sufficient evidence to the national assessment team. The evidence could be written documents, photographs and videos but it should be authenticated by the team.

However a PIA can file an appeal to MoRD. MoRD should give its decision within 20 working days and that will be treated as binding. However, if MoRD does not give decision in 20 days, then the decision taken by NIRD&PR will be considered final.