5.2. Inspection of training centre

Overview

Item

Description

Purpose

To describe inspection procedures to:

  • ensure compliance of earlier checks
  • check the documentation
  • assess the quality of training and
  • overall performance of training centres

Reference to guidelines

Para 3.2.1.7, page 23

Prerequisite/s                  

Access to completed:

Time for completion                  

As per the inspection schedule

Resource/s

SF 5.2A: Training centre inspection and as per the SFs listed after the activities table below

Process owner

PIA OP team

Activities

Actor

Action

Time for completion

Relevant documents

PIA OP team

To ensure

  • Availability of all recordsas per list given in due diligence and information about the activities to be carried out at the centre on ERP
  • Proper functioning of the training centre

Duration varies as per each activity and time for completion is shown against the activity

 

SF 5.2A: Training centre inspection and as per forms listed in due diligence list.

PIA Q team

carry out the inspection as detailed in SF 5.2A

Share inspection report and advisories with SRLM/CTSA

Follow up for compliance

As per the inspection schedule

SF 5.2A 

For APS

SRLM

  • Carry out the inspection as detailed in SF 5.2A
  • To verify randomly selected items verified by PIA Q team including the inspection notes and compliance of the PIAs Q team
  • Share inspection report and advisories with PIA for compliance and CTSA for information

As per the inspection schedule

Within 3 days of conduct of inspection

SF 5.2A

CTSA

  • Carry out the inspection as detailed in SF: 5.2A
  • Check on Q team and SRLM reports and share the advisories
  • Share inspection report and advisories with PIA for compliance and SRLM to ensure

As per the inspection schedule

 

 

Within 3 days of conduct of inspection

 SF 5.2A

PIA OP team

  • Comply with the advisories shared

Within 5 days of receipt of advisories

SF 5.2A

PIA Q team
  • Ensure compliance of the advisories
Within 8 days of receipt of advisories SF 5.2A
SRLM
  • Verify compliance report of PIA Q team and initiate action as per default procedure and report CTSA
As per the schedule prescribed in Default chapter SF 5.2A

For YPS

CTSA

  • Carry out the inspection as detailed in SF: 5.2A
  • To verify randomly selected items verified by PIA Q team including the inspection notes and compliance of the PIAs Q team
  • Share inspection report and advisories with PIA for compliance and SRLM for information

As per the inspection schedule but not later than 3 days of inspection conducted

 

Within 3 days of conduct of inspection

SF 5.2A

5.2.1     Protocol for inspection of a training centre

All training centres will be inspected by persons trained in DDU-GKY processes. In emergencies if inspections are done by SRLM/CTSA/MoRD personnel not trained in DDU-GKY processes the same should be reviewed and ratified by personnel trained in DDU-GKY.

(If the centre does not run throughout the year, the number of inspections will be reduced proportionately but there should be at least one inspection by Q team in a year).

5.2.1.1     Deleted

Content of the section is deleted, however the section is retained to maintain the number continuity

5.2.1.2     PIA Q team

  • Q team will inspect a training centre at least 6 times in a year of which at least 4 will be planned inspections. These inspections should be staggered such that a centre is inspected around 40 days after a batch starts.
  • Remaining inspections will be surprise. During surprise visits the team should check 2 modules randomly picked by the system. In addition the team can choose two more modules as per the situational needs.

5.2.1.3     SRLM (or its TSA) for APS/CTSA for YPS

  • SRLM/CTSA will undertake around 4 inspections of a training centre per annum of which two will be detailed and two will be surprise. The inspections should be so staggered to cover all the batches trained in a centre.
  • Modules to be inspected during surprise check will be randomly generated by the ERP system. SRLM/CTSA can also choose additional items to be inspected as per their choice.
  • In addition to their regular inspections they will audit PIA Q team inspections.
  • CTSA inspections for YPS would be of the same nature as the SRLM of an APS.

5.2.1.4     CTSA (for APS and YPS)

  • CTSA will conduct the inspections to audit inspections of PIA Q team and the SRLM 
  • In this role CTSA will undertake at least 3 visits to a training centre - 2 surprise and 1 detailed
  • It will ensure that each centre will undergo due diligence inspection before initiation of training.
  • For APS SRLM will ensure compliance of its reports and CTSA reports.
  • For YPS CTSA will take corrective action based on its inspections and those undertaken by the SRLM.

5.2.1.5     Role of SRLMs in YPS

SRLM in an YPS can play an active role in ensuring quality of the programme. However, as SRLM team is not strengthened no schedules are prescribed for their inspections. Depending on the staff availability, SRLM is encouraged to get its personnel trained in DDU-GKY procedures and to enable monitoring by its team.

All inspection reports of SRLM of YPS should be sent to CTSA, PIA and MoRD. It is the responsibility of the PIA to comply with items and send a compliance report through the PIA Q team to SRLM and CTSA. CTSA will monitor and ensure proper compliance.

5.2.2     Protocol for CCTV

Overview

Item

Description

Purpose

To ensure that a training centre performs as per procedures in guidelines and the SOP by review of CCTV footage

Reference to Guidelines

Para 3.2.2.2.1, page 27

Prerequisite/s                   

Start of training centre

Time for completion                  

Continuous process when the training is going on

Resource/s

As per SF 5.2B: CCTV - Specifications, location and recording, review and storage

Process owner

PIA OP team

Activities

Actor

Action

Time for completion

Relevant documents

PIA OP team

  • To ensure that the daily activities are being captured through CCTV.
  • Storage of video footage after completion of each batch and share whenever is asked for

Daily

SF 5.2B: CCTV - Specifications, location and recording, review and storage

To review CCTV footage as per the instruction given in SF 5.2A: Training centre inspection

As per the inspection schedule

SF 5.2B

For APS

SRLM

  • To review CCTV footage as per the instruction given in SF 5.2A: Training centre inspection
  • To verify randomly generated samples verified by PIA Q team including the inspection notes and compliance of the PIAs Q team

As per the inspection schedule

SF 5.2B

CTSA

Check on Q team and SRLM reports

As per the inspection schedule

SF 5.2B

For YPS

CTSA

  • To review CCTV footage as per the instructions given in SF 5.2A: Training centre inspection
  • To verify randomly generated samples verified by PIA Q team including the inspection notes and compliance of the PIAs Q team
  • Follow up on compliance of SRLM’s observations.

As per the inspection schedule