3.3.Project Execution Readiness Assessment

Overview

Item

Description

Purpose

To ensure availability of basic core team for implementing the project and sensitize them in implementation procedures

Reference to Guidelines

 NA

Prerequisite/s                    

Uploading of sanction order on the designated website

Time for completion                  

Any time after issue of sanction order but not later than 30 days from release of 1st Instalment (not later than I +30) and continuous process for revision

Resource/s                

SF 3.3A: Project execution readiness assessment at Project Headquarter and SF 3.3A1: Project execution readiness assessment at PIA Headquarter

Process owner

PIA for all states

Activities

Actor

Action

Time for completion

Relevant Documents

PIA

  • Filling up all the details

  • Update planned change

  • Update unplanned change

Not later than I + 15 days

15 days before change

Within 48 hours of change

SF 3.3A: Project execution readiness assessment at Project Headquarter and SF 3.3A1: Project execution readiness assessment at PIA Headquarter

SRLM (for APS)/CTSA (for YPS)

  • Validation of data and visit of project Headquarter

First visit: Complete by I + 30 days

Other visits: Not specified but will be decided based on the quality of project implementation.

SF 3.3A: Project execution readiness assessment at Project headquarter

SRLM (for APS)/CTSA (for YPS)

  • Validation of data and visit of PIA Headquarter*.

To be done along with first month audit visit by Finance team.

Other visits: Not specified but will be decided based on the quality of project implementation subject to minimum of one visit in a year either by  CTSA or SRLM visit. Others can decide based on the visit report.

SF 3.3A: Project execution readiness assessment at Project Headquarter

Note: As a PIA may have projects spread out in many states the teams can plan the visits in consultation PIA and other states. If a SRLM/CTSA team visit is less than 6 months old, then PIA headquarter visit is optional. SRLM/CTSA can take a call depending on the situation.