8.11 Closure financial audit

8.11.1 Financial Audit for Project Closure

Overview

Item

Description

Purpose

Prior to the closure of project, audit needs to be conducted for

  • Closure of the project accounts.
  • Audit the transactions relating to any unaudited period.

Reference to Guidelines

Step 9, table 3, para 4.3, page 42

Section 4.11, page 52

Prerequisite/s

Completion of placement of candidates

Time for completion            

As per the activity table below

Instructions

SI 8.4A: Common instructions on payment of entitlements, SI 8.4B: Instructions on payment of food and transportation cost, SI 8.4C: Instructions on post placement support (PPS) payment, SI 8.4D: Instructions on one time travel support, SI8.4E: Instructions on accounting of boarding and lodging expenses, SI 8.5A: Instructions for payment of salaries to trainers, master trainers and Q team members, SI 8.10F: Items to be verified during closure audit and SI 8.10G: Sample size for verification of transactions

Process owner

For APS: SRLM finance team

For YPS: CTSA finance team

 

Activities

Step No.

Activities

Actor

Time for completion

Relevant documents

 1

Finalize and share closure financial audit certificate, Closure Utilization Certificate along with audited financial statements and books of account in accordance with the applicable standards and share along with other documents as required with Annual Auditor for audit

PIA OP Team (Finance)

Within 10 months of completion of placement of candidates

SF 8.11A: Consolidated Financial Audit Certificate (for complete project) and SF 8.11E: Consolidate Utilization Certificate (for complete project)

 2

Conduct Closure audit of books of account of unaudited period based on the sampling technique as per the applicable auditing standards with the sample size mentioned under SI 8.10G, as minimum

Annual Auditor

Within 1 month of sharing of books of account and other documents by PIA with Annual Auditor

SF 8.11A and SF 8.11E along with annual audited financial statements

 3

Authenticate Closure Audit Certificate and Closure Utilization Certificate along with audited financial statements based on the annual audits conducted during the entire project period and audit for unaudited periods

Annual Auditor

Within 1 month of sharing of books of account and other documents by PIA with Annual Auditor

SF 8.11A and SF 8.11E along with annual audited financial statements

4

Submit Closure Audit Certificate and Utilisation Certificate along with audited financial statements as it’s annexure to SRLM (in case of APS) and CTSA (in case of YPS)

PIA OP Team (Finance)

Within 5 days of submission of Closure Audit Certificate and Closure Utilisation Certificate by Annual Auditor

SF 8.11A and SF 8.11E along with annual audited financial statements

Reconcile the amount of expenditure for prescribed heads, assess deviations reported in closure audit certificate

 

SRLM finance team (in case of APS)

 

CTSA finance team (in case of YPS)

Within 15 days of submission of Closure Audit Certificate and Utilisation Certificate by PIA

SF 8.11A and SF 8.11E along with annual audited financial statements

Issue a Closure Verification Report directing the PIA to rectify deviations and report compliance

SRLM finance team (in case of APS)

 

CTSA finance team (in case of YPS)

Within 15 days of submission of Closure Audit Certificate and Utilisation Certificate by PIA

SF 8.11B: Interim Evaluation letter of SRLM/CTSA for Consolidated Utilization Certificate (for complete project period) submitted by PIA

 7

Comply with the Closure Verification Report of SRLM/CTSA and submit a Compliance Report

PIA OP Team (Finance)

Within 5 days of issue of Closure Verification Report by SRLM/CTSA as the case may be

 

SF 8.11C: Management response to be submitted by PIA to SRLM/CTSA

 8

Review the Compliance Report submitted by PIA and issue Final Closure Verification Report. Generate notice, in case of deviations not addressed.

 

 

SRLM finance team (in case of APS)

 

CTSA finance team (in case of YPS)

Within 15 days of submission of Compliance Report by PIA.

 

If the Final Closure Verification Report is not sent by SRLM/CTSA as the case may be then it is deemed that PIA’s compliance report is accepted

SF 8.11D: Final evaluation letter of SRLM/CTSA for Consolidated Utilization Certificate (for complete project period) submitted by PIA

8.11.2  Financial audit for orderly closure of a project

When a project cannot be executed and needs to be closed as per process 3.9 (ii) of SOP, the procedure for foreclosure will be followed.

  • The order for foreclosure proceedings will specify the conditions of closure
  • Closure audit will follow the all the processes prescribed for closure

Closure financial audit will be conducted as per orders given for closure of project. All the expenditure incurred till the completion would be accounted for subject to the budget limited to the achievement of the physical target. Annual auditor will follow all the procedures laid down in the process “8.11.1: Project Closure financial audit”.

 When a project is closed by MoRD through a closure order, expenditure incurred will be frozen after the issue of the order. The order will also specify the steps to be taken on training activities in progress on date of issue of the order and payment of entitlements to candidates.

 Activities other than those specified in the order for orderly closure will not be permitted to be initiated and any expenditure incurred on such activities. Annual auditor will follow all the procedures laid down in the process 8.11.1: Project Closure financial audit.