3.3.Project Execution Readiness Assessment
Overview
| 
 Item  | 
 Description  | 
| 
 Purpose  | 
 To ensure availability of basic core team for implementing the project and sensitize them in implementation procedures  | 
| 
 Reference to Guidelines  | 
 NA  | 
| 
 Prerequisite/s  | 
 Uploading of sanction order on the designated website  | 
| 
 Time for completion  | 
 Any time after issue of sanction order but not later than 30 days from release of 1st Instalment (not later than I4 +30) and continuous process for revision  | 
| 
 Resource/s  | 
 SF 3.3A: Project execution readiness assessment at Project Headquarter and SF 3.3A1: Project execution readiness assessment at PIA Headquarter  | 
| 
 Process owner  | 
 PIA for all states  | 
Activities
| 
 Actor  | 
 Action  | 
 Time for completion  | 
 Relevant Documents  | 
| 
 PIA  | 
  | 
 Not later than I4 + 15 days Within 48 hours of change  | 
SF 3.3A: Project execution readiness assessment at Project Headquarter and SF 3.3A1: Project execution readiness assessment at PIA Headquarter | 
| 
 SRLM (for APS)/CTSA (for YPS)  | 
  | 
 First visit: Complete by I4 + 30 days Other visits: Not specified but will be decided based on the quality of project implementation.  | 
SF 3.3A: Project execution readiness assessment at Project headquarter | 
| 
 SRLM (for APS)/CTSA (for YPS)  | 
  | 
 To be done along with first month audit visit by Finance team. Other visits: Not specified but will be decided based on the quality of project implementation subject to minimum of one visit in a year either by CTSA or SRLM visit. Others can decide based on the visit report.  | 
 SF 3.3A: Project execution readiness assessment at Project Headquarter  | 
| Note: As a PIA may have projects spread out in many states the teams can plan the visits in consultation PIA and other states. If a SRLM/CTSA team visit is less than 6 months old, then PIA headquarter visit is optional. SRLM/CTSA can take a call depending on the situation. | |||