Site: | eSOP Learning Portal |
Course: | Operations |
Book: | Content |
Printed by: | Guest user |
Date: | Thursday, 24 July 2025, 1:10 AM |
Overview
Item |
Description |
Purpose |
To lay down MoU execution process and related timelines |
Reference to Guidelines |
|
Prerequisite/s |
Uploading of approved empowered committee (EC) minutes and sanction order |
Time for completion |
20 working days from uploading of sanction order on the nominated website (Sanction order uploading day is referred as ‘I2’) |
Resource/s |
As per SF 3.1A: Prospective project work schedule, SF 3.1B: Standard terms & condition, SF 3.1.C: Special terms & conditions and SF 3.1.D: Power of Attorney (PoA) |
Process owner |
For APS: SRLM For YPS: CTSA |
Overview
Item |
Description |
Purpose |
To delineate the preparatory work for MoU execution and related timelines |
Prerequisite/s |
Uploading of EC minutes on the nominated website |
Time for completion |
15 days of time gap between I1 and I2 and 2 days after I2(I1: Uploading of approved EC minutes and I2: Uploading of Sanction order) |
Resource/s |
As per SF 3.1A: Prospective project work schedule, SF 3.1B: Standard terms & condition, SF 3.1.C: Special terms & conditions and SF 3.1.D: Power of Attorney (PoA) |
Process owner |
For APS: SRLM For YPS: CTSA |
Activities
Sl. |
Action |
Actor |
Time for completion |
Relevant documents |
For YPS |
||||
1 |
Filling up “Prospective project work schedule” |
PIA |
I1 + 10days |
SF 3.1A: Prospective project work schedule |
2 |
Review of “Prospective project work schedule”[1] |
SRLM |
I1 + 15 days |
Review and validate SF 3.1Aas per 3.1.1.1 of SOP |
3 |
Validation of “Prospective project work schedule” |
CTSA |
I1+ 17days |
validate and freeze SF 3.1A as per 3.1.1.1 of SOP |
4 |
Preparation of MoU annexures |
PIA |
I1+3 days |
SF 3.1B: Standard terms & condition, SF 3.1.C: Special terms & conditions and SF 3.1.D: Power of Attorney (PoA) |
5 |
Filling up MoU signatory by name & designation |
PIA, SRLM &CTSA |
I1 +3 days |
On the designated website |
6 |
Review fund position and advise MoRD and/or SRLM if funds are likely to fall short with a copy to PIA |
CTSA |
I1 +3 days |
As per data given in ERP system. |
For APS |
||||
1 |
Filling up “Prospective project work schedule” |
PIA |
I1 +10 days |
SF 3.1A |
2 |
Validation of “Prospective project work schedule” |
SRLM |
I1 +17 days |
validate and freeze SF 3.1A as per 3.1.1.1 of SOP below |
3 |
Preparation of MoU annexures |
PIA |
I1 +3 days |
SF 3.1B, 3.1.1C and 3.1.1D |
4 |
Filling of MoU signatory by name & designation |
PIA and SRLM |
I1 +3 days |
On the designated website |
5 |
Review fund position and advise MoRD or take internal action if funds are likely to fall short with a copy to PIA. |
SRLM |
I1 +3 days |
As per data given in ERP system. |
The prospective work schedule for the project should give a comprehensive picture of PIA’s plan of action for implementing the project. The details are to be filled in a web form as per SF 3.1A and would include the following:
a. Monthly training commencement schedule for the complete project duration.
b. Monthly training completion schedule for the complete project duration.
c. Training of candidates should commence within 90 days of project commencement date.
Figure 3.1‑1 Preparatory steps in execution of MoU for YPS
d. Minimum trainings to be initiated in a year as per the project duration is given below:
e. Within the minimum targets prescribed above the PIA has flexibility to vary the training quantum across different months of the year, across different geographical locations, across different trades and training centres.
f. Within the minimum yearly targets prescribed above the PIAs has flexibility to revise the PPWS as per the conditions prescribed below:
Any deviation from PPWS will lead to:
Overview
Item |
Description |
Purpose |
To delineate the steps/actions to be taken in signing MoU |
Prerequisite/s |
Uploading of sanction order on the nominated website |
Time for completion |
20 working days from uploading of sanction order (start from I2day) |
Resource/s |
MoU |
Process owner |
For APS: SRLM For YPS: CTSA |
Activities
Sl. |
Action |
Actor |
Time for completion |
Relevant Documents |
For YPS |
||||
1 |
Review highlighted text of system generated MoU |
PIA & SRLM |
I2+2 days |
MoU |
2 |
Vetting and freezing of MoU and annexures thereof |
CTSA |
I2+4 days |
MoU |
3 |
Printing and signing of MoU and annexures, and ensure that it reaches SRLM |
PIA |
I2+7 days |
From the above source |
4 |
Signing of MoU and ensuring that it reaches CTSA |
SRLM |
I2+14 days |
MoU |
5 |
|
CTSA |
I2+20 days |
MoU and uploading on the designated website |
For APS |
||||
1 |
Review highlighted text of system generated MoU |
PIA |
I2+2 days |
MoU |
2 |
Vetting and freezing of MoU and annexures thereof |
SRLM |
I2+4 days |
MoU |
3 |
Printing and signing of MoU and annexures, which should reach at SRLM |
PIA |
I2+7 days |
From the above source |
4 |
Signing of MoU sending a copy to PIA and informing CTSA about the event completion Uploading MoU and annexures on the web-link |
SRLM |
I2+14 days |
Project MoU and uploading on the designated website |
Figure 3.1‑2 Execution of MoU for YPS
Overview
Item |
Description |
Purpose |
To lay down the fund release process for 1st instalment and issue of Project commencement order to PIA |
Reference to Guidelines |
|
Prerequisite/s |
Uploading of executed MoU |
Time for completion |
10 working days after signing the MoU (MoU execution day is coded as I3) |
Resource/s |
As per SF 3.2A: Project account registration form on PFMS and SF 3.2B: Project commencement order and SI 8.3D1: Applicability and settlement of TDS |
Process owner: |
For APS: SRLM For YPS: CTSA |
Activities
Actor |
Action |
Time for completion |
Relevant Documents |
PIA |
|
To be completed at least 5 days before signing of MoU (I3-5 days) |
SF 3.2A: Project account registration form on PFMS |
SRLM (For APS)/ CTSA (For YPS) |
Release the first instalment amount of central & State shares after deduction of TDS and updating the status on designated web-link (It is mandatory central and state shares are released together This should be followed meticulously by fund releasing agencies) |
latest by I3+10 days |
SI 8.3D1: Applicability and settlement of TDS |
SRLM (For APS)/ CTSA (For YPS) |
Issue of Project commencement order |
latest byI3+10 days |
|
Note: The project commencement date of the project will be from 30 days from the date release of central and state share from CTSA for YPS/ SRLM for APS |
CTSA must release funds to the PIAs only after it receives both the central and state shares. In some cases the central share was released before the SOP was issued with the instructions that PIA should not spend any money till SOP is released. Now it is reiterated that PIA should not spend any money till state share is released.
[1] If consortium partners are going to implement any activities and any outsourcing partner is engaged in training and placement towards the project, they have to open a dedicated bank account. All the project bank account needs to be mapped into PFMS, whenever the system becomes functional.
Overview
Item |
Description |
Purpose |
To ensure availability of basic core team for implementing the project and sensitize them in implementation procedures |
Reference to Guidelines |
NA |
Prerequisite/s |
Uploading of sanction order on the designated website |
Time for completion |
Any time after issue of sanction order but not later than 30 days from release of 1st Instalment (not later than I4 +30) and continuous process for revision |
Resource/s |
SF 3.3A: Project execution readiness assessment at Project Headquarter and SF 3.3A1: Project execution readiness assessment at PIA Headquarter |
Process owner |
PIA for all states |
Activities
Actor |
Action |
Time for completion |
Relevant Documents |
PIA |
|
Not later than I4 + 15 days Within 48 hours of change |
SF 3.3A: Project execution readiness assessment at Project Headquarter and SF 3.3A1: Project execution readiness assessment at PIA Headquarter |
SRLM (for APS)/CTSA (for YPS) |
|
First visit: Complete by I4 + 30 days Other visits: Not specified but will be decided based on the quality of project implementation. |
SF 3.3A: Project execution readiness assessment at Project headquarter |
SRLM (for APS)/CTSA (for YPS) |
|
To be done along with first month audit visit by Finance team. Other visits: Not specified but will be decided based on the quality of project implementation subject to minimum of one visit in a year either by CTSA or SRLM visit. Others can decide based on the visit report. |
SF 3.3A: Project execution readiness assessment at Project Headquarter |
Note: As a PIA may have projects spread out in many states the teams can plan the visits in consultation PIA and other states. If a SRLM/CTSA team visit is less than 6 months old, then PIA headquarter visit is optional. SRLM/CTSA can take a call depending on the situation. |
Overview
Item |
Description |
Purpose |
To specify activities for release of 2nd instalment of funds to PIA |
Reference to Guidelines |
|
Prerequisite/s |
System generated notification for fulfilment of condition as per above reference to guidelines |
Time for completion |
60 working days for YPS (40 working days for APS) from eligibility day (notification date of eligibility for 2nd instalment is coded as E2) provided all conditions are fulfilled by the PIA. |
Resource/s |
SF 3.4A: Checklist for release of 2nd instalment updated through the system and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment. |
Process owner |
for APS: SRLM for YPS 1) CTSA till dispatch of recommendation to MoRD and also for release of funds after MoRD issues release order 2) MoRD after receipt of recommendation and till issue of release order |
Activities
Actor |
Action |
Time for completion |
Relevant Documents |
PIA |
Submission of checklist and annexures for release of 2nd instalment to SRLM for APS/CTSA for YPS |
E2+3 days |
SF 3.4A: Checklist for release of 2nd instalment updated through the system and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment |
SRLM for APS/CTSA for YPS |
Ensure all advisories are complied with CTSA to SRLM for APS and vice-versa for YPS. Validate the checklist, annexures and upload on designated web-link.[1] |
E2 +10 days |
Inspection reports of PIA Q team, SRLM/CTSA and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment |
For APS |
|||
SRLM (APS) |
|
Before E2+40 days |
SI 8.3D1: Applicability and settlement of TDS |
For YPS |
|||
CTSA
|
Recommendation for release of 2nd instalment to MoRD |
E2 +12 days |
SF 3.4A: Checklist for release of 2nd instalment updated through the system |
MoRD |
Issue of release order and upload on the designated web-link |
E2+ 52 days |
Nil |
CTSA |
Release of 2nd instalment to PIA after deducting TDS and upload the status on the designated web-link |
E2+60 days |
SI 8.3D1: Applicability and settlement of TDS |
[1]If a PIA fails to comply with the conditions for release of instalment then the request for release will be sent to the bottom of queue.
Overview
Item |
Description |
Purpose |
To delineate steps in release of 3rd instalment to PIA |
Reference to Guidelines |
|
Prerequisite/s |
System generated notification for fulfilment of condition as per above reference to guidelines |
Time for completion |
60 working days for YPS (40 working days for APS) from eligibility day (notification date of eligibility for 3nd instalment is referred as ‘E4’ day) provided all conditions are fulfilled by the PIA. |
Resource/s |
SF 3.5A: Checklist for release of 3rd instalment and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment |
Process owner |
for APS: SRLM for YPS 1) CTSA till dispatch of recommendation to MoRD and also for release of funds after MoRD issues release order. 2) MoRD after receipt of recommendation and till issue of release order |
Activities
Actor |
Action |
Time for completion |
Relevant Documents |
PIA |
Submission of checklist and annexures for release of 3rdinstalment to SRLM for APS/CTSA for YPS |
E4+3 days |
SF 3.5A: Checklist for release of 3rd instalment and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment |
SRLM for APS/CTSA for YPS |
Ensure all advisories are compiled by CTSA to SRLM for APS and vice-versa for YPS. Validate the checklist, annexures and upload on designated web-link.[1] |
E4+10 days |
Inspection report of SRLM/CTSA |
For APS |
|||
SRLM (APS) |
|
E4+40 days |
SI 8.3D1: Applicability and settlement of TDS |
For YPS |
|||
CTSA
|
Recommendation for release of 3rdinstalment to MoRD |
E4+12 days |
|
MoRD |
Issue of release order and upload on the designated web-link |
E4+52 days |
Nil |
CTSA |
Release of 3rdinstalment to PIA after deducting TDS and upload the status on the designated web-link |
E4+60 days |
SI 8.3D1: Applicability and settlement of TDS |
[1]If it is found that, the PIA has fail to comply the Guidelines condition then the proposal for release will be sent back to the queue and the process will start afresh from the beginning
Overview
Item |
Description |
Purpose |
To verify and close the training and placement component of the project |
Reference to Guidelines |
NA
|
Prerequisite/s |
Completion of project training and placement activities |
Time for completion |
Complete within 70 days after the PIA completes the project training and placement process. (Date of completion of placement for the project is referred as ‘E7’ day). |
Resource/s |
|
Process owner |
For APS: SRLM/For YPS: CTSA |
Activities
Actor |
Action |
Time for completion |
Relevant Documents |
PIA op team |
1. Complete last batch of training and place minimum 75% of candidates thereof. System will freeze the training and placement data on the designated website 2. Provide the checklist as per standard format |
E6 for training and E7 for placement completion |
Nil |
PIA Q team |
Complete the verification of training and placement |
E7 + 20 days |
Nil |
SRLM (For APS)/ CTSA (For YPS ) |
Complete the verification of training and placement |
E7 + 20 days |
Nil |
SRLM (For APS)/ CTSA (For YPS) |
Validate the training and placement data on the designated website |
E7+ 35day |
Nil |
SRLM/CTSA |
Ensure all advisories are complied with – advisories from CTSA to SRLM for APS and vice-versa for YPS. |
E7+ 40 days |
Inspection report of Q teams of SRLM/ CTSA |
For APS |
|||
SRLM |
Verify the check list and finalise the total training and placement |
E7 + 45 days |
|
SRLM |
Issue Project completion report |
E7 + 70 days |
Nil |
For YPS |
|||
CTSA |
Verify the check list and finalise the total training and placement |
E7 +45 days |
|
CTSA |
Advise MoRD about the project closure of training and placement |
E7 +50 days |
Nil |
MoRD |
Issue project completion report |
E7 +70 days |
Nil |
Overview
Item |
Description |
Purpose |
To lay down the fund release process of 4th instalment to PIA & closure of the project |
Reference to Guidelines |
|
Prerequisite/s |
Fulfilment of condition as per reference to guidelines and notification for data freezing on the web-link |
Time for completion |
14 months from ‘E7’ day[1] |
Resource/s |
SF 3.7A: Checklist for release of 4th instalment and SF 3.7B Project completion report and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment |
Process owner |
SRLM for APS/CTSA for YPS |
Activities
Actor |
Action |
Time for completion |
Relevant Documents |
PIA op team |
Submission of project closure report and checklist and annexures for release of 4th instalment to SRLM and CTSA |
E7+10 months |
SF 3.7A: Checklist for release of 4th instalment, SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment and SF 3.7B Project completion report |
SRLM for APS/CTSA for YPS |
Completing the retention verification process |
E7+10 months 9 days |
Inspection report of SRLM/CTSA |
SRLM for APS/CTSA for YPS |
Verification and comments on Project closure report. Validate the checklist, annexures and upload on designated web-link. |
E7+10 months 14 days |
SF 3.7A: Checklist for release of 4th instalment, SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment and SF 3.7B Project completion report |
PIA |
Changes as per the comments of SRLM/CTSA (if any) |
E7+10 months 24 days |
|
SRLM for APS/CTSA for YPS |
Freezing and uploading of Project closure report on the designated web-link |
E7+ 11 months 8 days |
3.7B Project completion report |
For APS |
|||
SRLM |
|
E7+12 months
E7+12 months 7 days
E7+12 months 15 days E7+13 months
|
SI 8.3D1: Applicability and settlement of TDS |
For YPS |
|||
CTSA
|
Recommendation for release of 4th instalment to MoRD |
E7+11 months 20 days |
|
MoRD |
Issue of release order and upload on the designated web-link |
E7+13 months |
Nil |
CTSA |
Release of 4th instalment to PIA after adjusting/deducting TDS and upload the status on the designated web-link |
E7+13 months 15 days |
SI 8.3D1: Applicability and settlement of TDS |
MoRD |
Issue of final closure report |
E7+14 months |
|
The basic conditions to be fulfilled for participation of a consortium in DDU-GKY and/or franchising/outsourcing of some activities to other agencies will be as per conditions specified in the guidelines (refer section v and vi, para 4.7 pages 49, 50 and 47 respectively). These conditions will be enforced at the application stage. Following arrangements enable implementation of these conditions:
2. Outsourcing / Franchisee arrangement
The financial transactions will be transparent and done through PFMS. Till such time PFMS is in place all transactions between various agencies in the project should be done through the banking system only.
If these conditions are not met, a PIA is deemed to have defaulted and action can be initiated as per the rules.
A project can be closed/terminated under the following conditions:
Project manpower is broadly divided into the following three categories:
A PIA will have absolute discretion for recruitment of the project management team (other than Q team head) and operations team. However, each month he should inform the total number of people working in each category on a project. CTSA/SRLM will have the discretion to verify these details as per situational exigencies. These will be as per SF 3.10A: Details of centre in-charge and trainers.
Q team head and its composition should be as per agreed plan and the PIA should update the details on the web-link. Similarly changes in the composition of the team should be informed without fail. These should be reported as per SF 3.10B: Details of Q team members.
The Q team should be ring fenced from the PIA operational team and managerial team. Mechanism for ring fencing a PIA Q team is given as SF 3.10C: Ring fencing of Q team from operations – Compliances report from the management. PIA should comply with this procedure before the project is initiated..
If a PIA defaults in implementing a project, recovering government money paid to PIA after adjusting for expenses incurred as per guidelines and SOP is a critical activity. If the PIA fails to repay the amount it is necessary to invoke the revenue recovery act 1890 or other applicable Revenue Recovery or Public Demands Recovery Act of the state/UT.
The procedure to recover the Government dues is as follows:
SF 3.1A: Prospective project work schedule
SF 3.1B: Standard terms & conditions
SF 3.1C: Special terms & conditions
SF 3.2B: Project commencement order
SF 3.3A: Project execution readiness assessment
SF 3.4A: Checklist for release of 2nd instalment
SF 3.5A: Checklist for release of 3rd instalment
SF 3.7A: Checklist for release of 4th instalment
SF 3.7B: Project closure report on the completion of project
SF 3.10A: Details of Centre in-charge and trainers
SF 3.10B: Details of Q team members
SF 3.10C: Ring fencing of Q Team from operations – Compliance report from the management