Overview
|
Item |
Description |
|
Purpose |
To lay down the fund release process of 4th instalment to PIA & closure of the project |
|
Reference to Guidelines |
|
|
Prerequisite/s |
Fulfilment of condition as per reference to guidelines and notification for data freezing on the web-link |
|
Time for completion |
14 months from ‘E7’ day[1] |
|
Resource/s |
SF 3.7A: Checklist for release of 4th instalment and SF 3.7B Project completion report and SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment |
|
Process owner |
SRLM for APS/CTSA for YPS |
Activities
|
Actor |
Action |
Time for completion |
Relevant Documents |
|
PIA op team |
Submission of project closure report and checklist and annexures for release of 4th instalment to SRLM and CTSA |
E7+10 months |
SF 3.7A: Checklist for release of 4th instalment, SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment and SF 3.7B Project completion report |
|
SRLM for APS/CTSA for YPS |
Completing the retention verification process |
E7+10 months 9 days |
Inspection report of SRLM/CTSA |
|
SRLM for APS/CTSA for YPS |
Verification and comments on Project closure report. Validate the checklist, annexures and upload on designated web-link. |
E7+10 months 14 days |
SF 3.7A: Checklist for release of 4th instalment, SF 3.4B: Decision rules for release of 2nd, 3rd, 4th and final instalment and SF 3.7B Project completion report |
|
PIA |
Changes as per the comments of SRLM/CTSA (if any) |
E7+10 months 24 days |
|
|
SRLM for APS/CTSA for YPS |
Freezing and uploading of Project closure report on the designated web-link |
E7+ 11 months 8 days |
3.7B Project completion report |
|
For APS |
|||
|
SRLM |
|
E7+12 months
E7+12 months 7 days
E7+12 months 15 days E7+13 months
|
SI 8.3D1: Applicability and settlement of TDS |
|
For YPS |
|||
|
CTSA
|
Recommendation for release of 4th instalment to MoRD |
E7+11 months 20 days |
|
|
MoRD |
Issue of release order and upload on the designated web-link |
E7+13 months |
Nil |
|
CTSA |
Release of 4th instalment to PIA after adjusting/deducting TDS and upload the status on the designated web-link |
E7+13 months 15 days |
SI 8.3D1: Applicability and settlement of TDS |
|
MoRD |
Issue of final closure report |
E7+14 months |
|